IT之家 9 月 25 日消息,据英国《卫报》今天(25 日)报道,英国政府曾大力宣传的埃塞克斯郡劳顿大型数据中心项目将无法按原计划于明年启用,甚至可能拖到 2030 年代中期。

劳顿项目 2025 年公布时被称为英国最大的 AI 超级计算机,但供电难题意味着项目距离投入运行仍有很长一段时间。

Artist's impression of datacentre in Essex.

当前,该项目因无法在原定 2027 年启用前取得足够电力而面临新的难题。该超算由英国初创企业 Nscale 负责建设,这家企业今年又计划以 350 亿美元(IT之家注:现汇率约合 2,351.04 亿元人民币)估值上市。

报道披露,负责把项目接入当地电网的 UK Power Networks(UKPN)已告知 Nscale,电网要到 2030 年代初至中期才能为数据中心给出足够电力。

Nscale 回应称,劳顿项目仍将推进。供电难题迟迟找不到快速应对办法,也反映出能源供应正成为数据中心建设的一大障碍。

Nscale 还清空了原先的脚手架堆场,同时开始研究场址内自行发电的可行性,以及能否缩短电网接入所需时间。

英国天然气与电力市面办公室(Ofgem)此前警告,电力接入申请已浮现积压。数据表明,今年 6 月有 315 座数据中心正在排队接入英国电网,合计用电需要达到 73GW,而英国全国用电高峰需要仅为 45GW。

劳顿项目申请的供电容量最高达到 90MW,相当于约 31.5 万户家庭的用电量。

本文来源:https://www.ithome.com/1/007/228.htm
若有版权问题,请来信告知:13951431913#139.com 或在右方提交评论。

IT Home, September 25: According to The Guardian's report today (25th), the large data center project in Loughton, Essex, which was heavily promoted by the UK government, will not be able to go live next year as originally planned and may even be delayed to the mid-2030s.

When the Loughton project was announced in 2025, it was described as the UK's largest AI supercomputer, but power supply challenges mean it is still a long way from becoming operational.

Artist's impression of datacentre in Essex.

Currently, the project is facing new difficulties because it cannot secure enough electricity before its originally scheduled go-live date in 2027. The supercomputer is being built by UK startup Nscale, which this year also plans to go public at a USD 35 billion valuation (IT Home note: at the current exchange rate, equivalent to approximately RMB 235.104 billion).

The report revealed that UK Power Networks (UKPN), which is responsible for connecting the project to the local grid, has informed Nscale that the grid will not be able to provide enough electricity to the data center until the early to mid-2030s.

Nscale responded that the Loughton project will still proceed. The prolonged absence of a quick solution to the power supply problem also reflects how energy supply is becoming a major obstacle to data center construction.

Nscale has also cleared the original scaffolding storage yard and has begun studying the feasibility of on-site power generation, as well as whether the time required for grid connection can be shortened.

The UK Office of Gas and Electricity Markets (Ofgem) previously warned that a backlog has emerged in electricity connection applications. Data shows that in June this year, 315 data centers were in queue to connect to the UK grid, with combined electricity demand reaching 73GW, while the UK's national peak electricity demand is only 45GW.

The power supply capacity applied for by the Laughton Project reaches up to 90MW, equivalent to the electricity consumption of approximately 315,000 households.